A year after a neighborhood vote backed revised plans for two Reynoldstown blocks beside the BeltLine, the project still has not reached its next city entitlement filing. The Allen Morris Company says it expects to submit that application by the end of 2026, with demolition and construction targeted for the first quarter of 2028.
Nothing is being demolished or built yet at 205 Holtzclaw St. or 930 Mauldin St. The proposal remains roughly 350 apartments, about 8,000 square feet of retail, buried parking and a new trail connection. For neighbors, the filing is the next meaningful milestone. It should put the current apartment counts, building massing, trail connection and affordability election before the public.
When we covered the project in May 2025, these blocks were being positioned as a substantial mixed-use addition to the neighborhood’s BeltLine frontage. The proposed uses have largely held. The schedule has moved considerably later.
From a 2026 groundbreaking to a 2028 start
In October 2025, Allen Morris development associate William Bell said the partnership was working toward breaking ground in the fourth quarter of 2026, with the first phase delivering in 2028. The revised schedule calls for work to begin in the first quarter of 2028. Officials have said construction would take about 22 months, putting initial occupancy in late 2029 at the earliest.
The Reynoldstown Civic Improvement League voted on the revised Holtzclaw plans on Oct. 13, 2025: 60 percent in favor, 25 percent against and 15 percent abstaining. That was neighborhood support, not city approval. As of the November 2026 update, the development team had not submitted its formal entitlement application.
There is an important distinction between the two addresses. The parcel at 930 Mauldin St. SE already has multifamily entitlement. Allen Morris says its next city application will seek entitlement for a 208-unit apartment building at 205 Holtzclaw St. SE, part of the approximately 350 apartments proposed across both blocks.
The available record does not identify a cause for the schedule change. Neither the neighborhood vote nor the absence of a filing establishes that the city or project opponents held it up.
What the filing should clarify
The southern parcel, owned by Morrison Properties, is planned for roughly 8,000 square feet of patio-oriented retail, buried parking and a BeltLine connection from Fulton Terrace. It currently holds an empty lot and low-rise warehouse buildings formerly occupied by the DooGallery. The two project blocks sit just north of Madison Yards and the Metalwork Lofts townhomes.
The affordable-apartment count remains unknown. BeltLine inclusionary zoning applies, but the team has not publicly selected between reserving 10 percent of the applicable apartments for households earning no more than 60 percent of area median income or 15 percent for households earning no more than 80 percent. Those are ordinance options, not a project commitment, so there is no supported affordable-unit total to attach to the approximately 350-apartment proposal yet.
The application will allow residents to compare those details with the earlier plans. A neighborhood vote shows where the review stood in October 2025. The filing should provide a current proposal to examine.
One correction to our earlier coverage matters here. Our May 2025 video referred to the developer as “Star Metals.” The developer is The Allen Morris Company, which developed the Star Metals District in West Midtown. It is partnering in Reynoldstown with Morrison Properties and Metzger and Co., with both sections designed by Perkins&Will.
I see the proposed Fulton Terrace connection and patio-oriented retail as useful neighborhood pieces to evaluate alongside the apartments. But the practical milestone for residents is the city filing, not the projected groundbreaking. That is where the scale, access and affordability choices should become available for public review.
The revised schedule changes our expectation for when these blocks could begin changing. The application should give us something concrete to assess about how they would change.