Six vacant buildings are coming down where you turn off Peachtree Road onto Bennett Street, past the antique warehouses. Together, they account for approximately 75,000 square feet. The Atlanta Beltline expects demolition to finish by the end of 2026.

That is the visible part of a larger change. Over two years, the Beltline spent $29 million assembling 3.2 acres along Peachtree Road. On Oct. 22, officials also broke ground on the trail that will pass the property.

Northwest Trail Segment 2A is a 0.3-mile path running east from the southeast corner of Bobby Jones Golf Course, along Colonial Hills Circle, to the northeast side of the Georgia Power substation. Completion is expected in early 2028, connecting Collier Hills North and Colonial Homes with the completed Northside Trail and Northwest Connector Trail.

What is being built and what has to wait

The project includes a 14-foot-wide multi-use trail, an elevated structure, a pedestrian bridge, stormwater infrastructure, brownfield remediation, lighting, cameras, railings and Trees Atlanta landscaping.

Hasbun Construction is the contractor, PATH Foundation is the program manager and Heath & Lineback is the design team. As we previously reported, Hasbun received its notice to proceed on Sept. 21.

What Segment 2A does not provide is the permanent crossing beneath Peachtree Road.

That crossing belongs to Section B and depends on the Georgia Department of Transportation replacing the Peachtree Road bridge. The Beltline says GDOT’s work is currently scheduled to begin in 2028. No completion date for Section B has been published.

Until the underpass can be built, Segment 2A will include an interim connection to Peachtree Road. New pedestrian-focused signals are intended to support a safer street-level crossing while the remaining sections are completed.

Section C, a separate 0.1-mile piece running from Peachtree Road to Peachtree Park Apartments, is expected to begin construction in early 2027.

The practical result is that the new trail can open while the permanent Buckhead connection remains unfinished.

The $29 million property beside the trail

In November 2024, Atlanta Beltline Inc., working with Mayor Andre Dickens’ administration, paid $11 million for nearly an acre at 2110 Peachtree Road. The acquisition included the former Elleven45 Lounge and land needed for the trail.

In August 2025, the Beltline spent another $18 million to expand the property around Peachtree Road and Bennett Street. Together, the purchases created a 3.2-acre, $29 million site the Beltline’s first acquisition along Peachtree Road.

The purchase provides land for the trail, makes room for GDOT’s bridge project and gives the Beltline control of a future development site in one of Atlanta’s most expensive corridors.

The agency says the property will support affordable housing and affordable commercial space. Those are commitments about its intended use, not a development plan.

No site design, housing count, income restrictions, commercial square footage, budget or construction schedule has been announced. The Beltline says it will hold a planning and community-engagement process, but it has not published a date. Businesses at the western end of Bennett Street are expected to remain open during demolition.

Most of the Beltline follows former railroad property. The Northwest Trail does not have one continuous abandoned corridor through Buckhead, so the agency has had to assemble land and easements to create a route.

In September, the Beltline announced that it had secured all the property rights needed for the 22-mile mainline loop. The 20-year process involved approximately 200 parcels and more than $200 million. The organization says 78 percent of the loop is complete and continues to target 2030 for finishing it.

A separate delay farther north

This project should not be confused with Northwest Trail Segment 1.

As AVV reported in September, Segment 1’s suspension bridge over Peachtree Creek was disassembled after engineering concerns emerged. Its completion moved from June 2026 to mid-2028.

Different segment, contractor and bridge. That delay shows how complicated the northern corridor can be, but it does not establish that Segment 2A will face the same problems.

My Take

The 0.3-mile trail is funded, under construction and expected to give two neighborhoods a paved connection in early 2028. But the larger long-term decision sits on the 3.2 acres beside it. I will be watching three milestones: demolition finishing by the end of 2026, Section C starting in early 2027 and the Bennett Street planning process opening to residents.

That last date matters most. Before a design and development agreement exist, residents can still ask how many homes will be affordable, at what incomes, for how long and what affordable commercial space will mean for a business signing a lease.

If you live nearby, what would you want included in the Bennett Street development?